Assignment – Project Network Plan

Don't use plagiarized sources. Get Your Custom Essay on
Construction Project Management
Just from $13/Page
Order Essay

undefined

Nine activities have been estimated with duration ranging from 5 to 35 days.

undefined

 

undefined

Activities:

undefined

1. Excavation footing10 Days

undefined

2. Form and Pour Footing10 Days

undefined

3. Grade and Pour Slab on grade5 Days

undefined

4. Erect Building10 Days

undefined

5. Install Finish Elements10 Days

undefined

6. Procure Reinforcement Steel7 Days

undefined

7. Order and Deliver Metal Building30 Days

undefined

8. Rough in Electric & Plumbing15 Days

undefined

9. Procure Miscellaneous Building Material35 Da:

undefined

1. Draw Bar Chart

undefined

2. Draw Precedence Diagram

undefined

3. Find critical path and float